Support / Updating & baselines

Compare Two Schedule Versions with Claim Digger

Claim Digger compares two versions of a schedule field by field. Use it to find out what changed between updates, to check a subcontractor's revised schedule, or to support a claim.

Run a comparison

  1. Project tools ▾ → Claim digger.
  2. Choose the Left baseline.
  3. Choose the right side, or leave it on Current schedule.
  4. Click Dig.

It needs at least one captured baseline. See Set a baseline.

Read the results

  • Summary: activities added, removed, field changes, and dependencies added, removed, and changed
  • Category chips: filter to Dates, Duration, Costs, Progress, Codes, or General
  • Text filter: search by activity name, WBS, or field
  • Table: WBS, Task, Field, Old, New

The table shows up to 1,000 rows. Use CSV for the complete set, or Markdown for a readable report.

Tips

  • Changed logic is often more telling than changed dates. Check the dependency changes for removed links and new constraints.
  • Anyone with access to the project can run Claim Digger. It doesn't change anything.