Compare Two Schedule Versions with Claim Digger
Claim Digger compares two versions of a schedule field by field. Use it to find out what changed between updates, to check a subcontractor's revised schedule, or to support a claim.
Run a comparison
- Project tools ▾ → Claim digger.
- Choose the Left baseline.
- Choose the right side, or leave it on Current schedule.
- Click Dig.
It needs at least one captured baseline. See Set a baseline.
Read the results
- Summary: activities added, removed, field changes, and dependencies added, removed, and changed
- Category chips: filter to Dates, Duration, Costs, Progress, Codes, or General
- Text filter: search by activity name, WBS, or field
- Table: WBS, Task, Field, Old, New
The table shows up to 1,000 rows. Use CSV for the complete set, or Markdown for a readable report.
Tips
- Changed logic is often more telling than changed dates. Check the dependency changes for removed links and new constraints.
- Anyone with access to the project can run Claim Digger. It doesn't change anything.